Phase 1: Cleaning & Preparation
Phase 2: Seam Sealing & Watertighting
Phase 3: Topcoat Application
Phase 4: Necessary Repairs
Project Overview
Diversified Roofing Solutions was engaged to address persistent roof leaks affecting the gymnasium at the Full Blast Recreation Center in Battle Creek, Michigan. The facility serves as a major community recreation hub and includes a gymnasium and indoor waterpark complex.
The roof had experienced excessive water intrusion due to improper installation of a solar-powered water heating system that had previously been mounted on the roof. The installation resulted in significant membrane damage and localized insulation saturation.
The goal of the project was to restore the roof system’s waterproofing integrity while avoiding the cost and disruption of a full roof replacement.
Challenge
Inspection revealed that the solar heating system installation had compromised a large section of the EPDM membrane and underlying insulation. Numerous penetrations and improper detailing had resulted in ongoing leaks throughout the gymnasium roof area.
Additionally, portions of the insulation had become saturated, requiring removal and replacement before a long-term restoration system could be installed.
Because the facility operates as a public recreation center and waterpark, minimizing disruption to daily operations was a key priority.
Implemented Solution
Diversified Roofing Solutions implemented a targeted repair and restoration approach designed to permanently resolve the damaged roof section while extending the service life of the entire roof system.
The project scope included:
- Removal of approximately 8,400 square feet of existing EPDM where the solar system had previously been installed
- Removal of approximately 8,400 square feet of saturated insulation board
- Installation of new ISO insulation board in accordance with manufacturer specifications and local building code requirements
- Installation of 8,400 square feet of new Elevate EPDM membrane to match the existing roof system
- Full preparation and reinforcement of the roof surface
- Application of a GAF High Solids Silicone restoration system across the EPDM roof assembly
The silicone coating system was applied at a rate of 2.5 gallons per square, creating a seamless waterproof membrane across the roof surface.
Warranty
The completed roof system qualified for:
- 20-Year GAF Emerald Pledge Manufacturer Warranty
- 2-Year Diversified Roofing Solutions Workmanship Warranty
This provides the facility with long-term protection and manufacturer-backed performance coverage.
Result
The restoration approach allowed the facility to resolve all active leaks while avoiding the need for a full roof replacement.
Project Cost: $104,000
Estimated Replacement Cost: $342,000
This solution delivered a capital savings of over $238,000 while extending the service life of the roof system for decades.
The project was completed with minimal disruption to the facility’s operations, allowing the recreation center and waterpark to remain fully operational during the work.
Let’s Build Predictability Into Your Portfolio.
Whether you manage ten assets or ten thousand, DRS Nationwide delivers the structure, transparency, and execution discipline your portfolio demands.